Task |
Status |
Description |
Dependencies |
Required materials
|
Joint walls |
Completed |
|
|
Already in Bancroft
|
Sand walls/ceiling |
Completed |
Lightly sand the walls/ceiling with a fine grit paper. The aim is to just smooth the joint cement where it meets the plasterboard, and knock off any lumps. Toilet and office have been done, with the exception of the cupboard area |
|
Sander and sanding disks in Bancroft
|
Seal walls/ceiling |
Completed |
Paint over walls with plasterboard sealer/primer. Toilet and kitchen area done |
Sanded walls |
Already in Bancroft
|
Paint walls/ceiling |
Completed |
Paint walls and ceiling. Toilet and kitchen area to be painted with hardwearing paint (Dulux Diamond Matt). Everywhere else in bare-plaster white matte trade paint (ie, no sealing required on the other walls) |
|
Brushes, rollers, white matt trade paint
|
Fit lights |
Completed |
Cut holes where necessary for lights (some are already cut from having been fitted before) and clip lights into place |
Ceiling painted |
Already in Bancroft
|
Corner angles |
Completed |
Fit protective aluminium corner angles to external corners on walls and around doorways |
Walls painted |
Angle pieces and contact adhesive (Evostik "Sticks like...") in Bancroft. Need some way to cut aluminium
|
Window sills |
Completed |
Fit sills to windows |
Walls painted |
Window sills, GripFill
|
Seal around windows |
Completed |
Remove protective film from windowframes and run sealant around the join between the windows and the walls |
Walls painted, sills fitted |
Suitable sealant (Wickes frame sealant) in Bancroft
|
Fit door stops |
Completed |
Fit stops to frames of toilet and office/workshop door |
|
Required wood, etc, in Bancroft
|
Paint doorframes |
Completed |
Paint doorframes |
|
Brushes, undercoat and gloss paint in Bancroft. Need some sort of flooring protection
|
Trim central doors |
Completed |
Trim a few mm of the bottom of the centre doors, so they don't stick on the carpet |
|
Electric plane (or manual plane if you're a masochist in need of some exercise)
|
Paint doors |
Completed |
Paint the doors |
|
Brushes, undercoat and gloss paint in Bancroft.
|
Fit toilet floor |
Completed |
Fit (or have fitted) a floor to the toilet |
|
|
Fit toilet |
Completed |
Fit the toilet |
Toilet floor |
Need waste plumbing connectors and screws to hold it down
|
Fit toilet sink and grab handles |
Completed |
Fit the sink and the various grab handles which the disabled loo needs |
Toilet walls/ceiling painted |
Dot-and-dab wall plugs (in Bancroft)
|
Plumb in toilet and sink |
Completed |
Plumb in sink (hot and cold) and toilet (cold), leaving tees to allow connections to workshop sink |
Sink/toilet fitted, kitchen plumbing done, holes drilled for pipes to workshop |
TMV in Bancroft
|
Fit toilet accessories |
Completed |
Fit bits and pieces to make the toilet useful: Toilet paper holder, soap dispener(?), paper towel holder(?), mirror, shelf for spare rolls, etc |
Toilet walls/ceiling painted |
Need to buy all these things
|
Fit toilet door |
Completed |
Fit the door, grab handle for the door, locking hardware |
Stops fitted, office floor fitted |
Door, hinges, disabled toilet locks. Grab handle came as part of toilet pack
|
Fit toilet switches, emergency light |
Completed |
Fit the lighting pull switch, emergency pull switch and reset button. Fit the emergency light (currently in the loft) |
Toilet walls/ceiling painted |
Everything already in Bancroft
|
Fit toilet fan |
Completed |
Fit the fan, connect to toilet light with an off-delay, duct the air to the outside world somehow |
Toilet walls/ceiling painted |
Fan, ducting, some way to get out through the back wall
|
Fit disabled alarm |
Completed |
Fit the alarm outside the toilet. Note that there is a spare cable for future expansion (a second alarm) |
Office wall painted |
Already in Bancroft
|
Privacy film |
Completed |
Fit privacy film in toilet and cupboard windows |
Walls/ceiling painted |
Privacy film, window cleaner, squeegee
|
Box in meter/fusebox |
Completed |
Hide the fusebox away in some nice boxing-in. Needs to be able support worktop and allow access to fusebox |
Kitchen painted |
Some 34mm^2 wood in space can be used for frame. Need to buy material to cover box, possibly hinges to allow access to fusebox/meter
|
Block unused drains |
Completed |
Seal up unused drains below the floor |
|
Expanding foam and/or cement
|
Office floor |
Completed |
Some sort of floor, to be decided. |
Office walls/ceiling painted, unused drains sealed |
Suitable flooring
|
Skirting board |
Mostly done. Some needs sticking down |
Skirting boards around office floor |
Office walls/ceiling painted. Floor done? |
Skirting board (wood/acrylic?)
|
Aircon cage |
Completed |
Build a cage to house the exterior A/C unit |
|
Being built using old toilet gates (recyling FTW)
|
Fit external aircon |
Completed |
External A/C unit, power switch and cage fitted. |
Cage |
External A/C unit, pipes, external cut-off switch in Bancroft. Need exterior-grade mains cable?
|
Fit office aircon |
Completed: A/C unit mounted. Engineer commissioned the system |
Fit internal A/C unit |
External A/C unit |
F-Gas engineer
|
Build kitchen units |
Completed |
Assemble the kitchen units (500mm, 925mm corner, 600mm cupboard) |
|
Everything already in Bancroft
|
Fit cupboard unit in kitchen |
Completed |
Cupboard->wall |
Kitchen walls/ceiling painted, unit built |
Everything (cupboard, dot&dab drywall plugs) already in Bancroft
|
Fit units |
Completed |
Units in place. Fit end board and plinth |
Kitchen walls/ceiling painted, units built |
Everything already in Bancroft
|
Water heater |
Completed: Mounted to wall. Plumbing and wiring done; it makes hot water. |
Heater bought and fitted, needs plumbing in |
Units built and fitted. Probably easier done before worktop goes on, but not essential |
Pretty much everything needed has been bought
|
Fit worktop and sink |
Completed |
Worktop on units, sink in worktop |
Units built |
Jigsaw, steady hand. Worktop & sink already in Bancroft.
|
Plumb in sink |
Completed |
Connect the sink up the hot and cold water, drain |
Worktop & sink fitted, water heater fitted |
May need some 15mm pipe connectors. Will need some drain pipe/connectors
|
Kitchen splashback |
Completed |
Fit splashback above sink area |
Worktop/sink fitted |
Need some sort of splashback
|
Fit trunking |
Complete |
Fit trunking to kitchen and office walls |
Office walls/ceiling painted |
Trunking already in Bancroft. May need extra ends/corners.
|
Fill walls in cupboard area |
Completed |
Fill in any holes with suitable filler |
|
|
Paint cupboard walls/ceiling |
Completed |
Paint walls and ceiling in cupboard area |
|
Brush, roller, white matt trade paint
|
Cover soil pipes in cupboard |
Completed |
Cover the holes in the cupboard walls where the soil pipes enter the floor, in such a way that we can get to them if necessary. Something like an acrylic sheet screwed over the gap |
Cupboard walls painted |
Sheet, screws, wallplugs, countersink washers
|
Cap off plasterboard edge in cupboard |
Completed |
Where the plasterboard stops in the cupboard area, use a strip of 12-15mm corner angle to protect the edge |
Cupboard walls painted |
Aluminium angle, contact adhesive
|
Run pipes for dirty workshop sink |
Completed |
Drill holes through walls to allow hot and cold pipes to pass through from the toilet to the dirty workshop, running along the back wall of the building |
|
Drills, pipe, pipe clips, etc, already in Bancroft
|
Fit wiring and sockets |
Completed. 30 double sockets in 5 RCBO-protected circuits |
Wire up the trunking, fit a switch to turn off several sockets at once for laser cutter |
Toilet walls/ceiling painted |
Need cable, trunking back-boxes, sockets, switch for laser cutter
|
Fit external socket |
Completed |
A waterproof 13A socket (or two) one the external back wall, so we can power things outside if the need arises. Switched from inside, so people don't steal our 'leccy |
Trunking in place |
External socket, trunking-mounted internal switch
|
Fit external tap |
|
An outside tap on the back wall, plus an internal tap to stop miscreants playing with the external tap |
Toilet plumbing |
External tap, internal tap, some pipe
|
Laser cutter extraction |
Completed |
Some sort of extraction to be fitted somehow |
Walls/ceiling painted, trunking in place |
Will need materials for this
|
Loft hatch |
Completed |
Fit a loft hatch |
|
Will need materials for this
|